Tagged: Road works

Tack Coat 1

Construction Methodology of Tack Coat

Tack Coat shall consist of an application of a single coat low viscosity liquid bituminous material on primed surface or bituminous surface under clause 503 of MORT&H specification. MACHINERY Bitumen pressure sprayer Balance Plates...

Pipe Culvert 1

Construction Methodology of Pipe Culvert

Pipe Culvert work shall consist of furnishing and providing plain and reinforced cement concrete pipes, of the type, diameter and length and length required at the locations as per drawing. MACHINERY Excavator Generator Tippers...

0

Construction Methodology of Prime Coat

Prime Coat shall consist of the application of a single coat of low viscosity liquid bituminous material to a porous granular surface in accordance with clause 502 of MORT&H specification. MACHINERY Bitumen pressure sprayer...

Wet Mix Macadam 0

Construction Methodology of Wet Mix Macadam(WMM)

This work shall consist of laying spreading and compacting clean, crushed, graded aggregate and granular material, pre-mixed with water, to a dense mass on prepared and approved granular sub-base in accordance with clause 406...

GSB 4

Construction Methodology of Granular Sub base(GSB)

Granular Sub Base (GSB) shall consist of laying and compacting well-graded material on prepared and approved subgrade in accordance with clause 401 of MORT&H specification. In other words, GSB is laid in between the...

Subgrade 1

Construction Methodology of Sub Grade

Sub Grade work shall consist of laying, spreading and compaction subgrade layer as per contract drawings with approved and specified material following cause 305 of MORT&H specification. MACHINERY Excavator Dumpers Dozer Motor Grader Vibratory...

Embankment 0

Construction Methodology of Embankment

SCOPE This work deals with laying, spreading, and compacting embankment layers with approved materials as per clause 305 & 900 of MORT&H specification. MACHINERY Excavator End Dumper Dozer Motor Grader Water tanker with sprinkler...

Site Clearance 0

Construction Methodology of Site Clearance

Clearing of land for preparation of the site to start construction activities is called Site Clearance. In other words, Site Clearance is the preliminary/initial process to start the work for construction. This work shall...

Rockfill Embankment 1

Construction Methodology of Rockfill Embankment

SCOPE The work covers embankment constructed with pieces of rock and shall be in accordance with the lines, graded, and cross-section as shown in drawings or as directed by the Engineer. There shall be...

Methodology of Earthwork 0

Construction Methodology of Earthwork

SCOPE This work shall consist of excavation, removal and satisfactory disposal of all materials necessary for the construction of roadways in accordance with requirements of MORT&H specifications and the lines, grades and cross-section shown...